TY - JOUR ID - TI - Reducing Times of Completion in Constructing Projects using The network Analysis Model of Business : Research Applied to the Bridge of the city of Baquba in The Brovince of Diyala" استخدام أنموذج التحليل الشبكي للأعمال لتقليل أوقات الإنجاز في المشاريع الإنشائية " بحث تطبيقي لمجسر مدينة بعقوبة في محافظة ديالى AU - حيدر شاكر نوري AU - كريم قاسم محمد PY - 2018 VL - IS - 32 SP - 170 EP - 195 JO - Journal of Al-Ma'moon College مجلة كلية المأمون SN - 19924453 27902544 AB - Many projects are missing out on their work according to a scientific method despite the major developments taking place in the world, which will make them to gain the advantage of speed of achievement, as well as the large cost of the completion of projects, Hence, the research aims to apply the network analysis to plan and follow the project of the bridge of the city of Baquba in the province of Diyala as a sample for research, to apply the slope cost method to determine the times required for completion and to determine the flat time of project activities, To reduce the normal time to complete the project according to the experimental time, the cost of evasion and, the best times and costs of the project were reached, In the light of this, a set of recommendations have been formulated which are hoped to be used by the specialists .

تفتقر الكثير من المشاريع إلى إنجاز أعمالها وفق أسلوب علمي على الرغم من التطورات الكبيرة التي يشهدها العالم، الأمر الذي سيفوت عليها كسب ميزة سرعة الإنجاز، فضلاً عن التكلفة الكبيرة المترتبة على إنجاز المشاريع، ومن هنا جاء البحث بهدف تطبيق التحليل الشبكي لتخطيط ومتابعة مشروع مجسر مدينة بعقوبة في محافظة ديالى كعينة للبحث، بتطبيق طريقة ميل الكلفة slop cost لتحديد الأوقات المطلوبة للإنجاز وتحديد الوقت الفائض لنشاطات المشروع لتقليل الوقت الطبيعي لإنجاز المشروع إلى الوقت التعجيلي، والكلفة التعجيلية، وتم التوصل إلى الأوقات والكلف الأفضل للمشروع، وعلى ضوء ذلك تم صياغة مجموعة توصيات يؤمل أن يستفيد منها المعنيون في البحث الحالي . ER -