TY - JOUR ID - TI - TIME-CONSTRAINS PROJECT SCHEDULING PROBLEM WITH ACTIVITIES ALTERNATIVES, ANT COLONY OPTIMIZATION APPROACH AU - Faiz Faiq Showkat PY - 2009 VL - 12 IS - 1 SP - 134 EP - 142 JO - Al-Nahrain Journal of Science مجلة النهرين للعلوم SN - 26635453 26635461 AB - In this paper we handle the problem of scheduling/rescheduling project activities when there is more than one method (alternatives) available to execute the project activities, each method has its own time duration and resource requirements and also there is a dependency between the methods of execution the activities , A suggested method is presented here to deal with activities dependency and the ant colony optimization metaheuristic approach is used to find the best set of alternatives for the project activities in order to finish the project as soon as possible and identifying the critical path of the project.

تم هنا تناول مشكلة جدولة/ اعادة جدولة للمشاريع التي تتألف من فعاليات تتوفر لها اكثر من طريقة لتنفيذ تلك الفعاليات (بدائل) ولكل طريقة زمنها وكلفتها الخاصة بها، تم اقتراح طريقة لتمثيل تلك البدائل واستخدام اسلوب مستعمرة النمل لايجاد افضل مجموعة بدائل بهدف انجاز المشروع باقصر وقت ممكن وتحديد المسار الحرج. ER -