استراتيجية استخدام أساليب جدولة المشروع ، بيرت والمسار الحرج في المفاضلة بين الوقت والتكلفة لانجاز المشاريع

Abstract

Time & cost considered a mijor factor in the success of the projects and methods of project scheduling ,PERT &C.P.M.give us auseful information to analyse & control the projects network in order to achieve the optimum to establish the project according to the resources in hands with the minium cost possible.In this research the project suppose to be achieved during (60) day, but it is achieved with in (108) day,while the critical activities are (1,2,3,4,5,6,9,10,11).